After
the last blog about the Templeton Elementary School Building meeting…Notes
from… ,there were some comments made about the contract for $900,000 with
the OPM.
MSBA
rules and regs have changed since our elementary school project began. One of
the new rules when we started the project was that in order to facilitate the
feasibility study and get the project to schematic design, communities needed
to select an OPM from a list of MSBA approved vendors. So we did. The Templeton
Elementary School Building Committee(TESBC) did an RFP and selected Strategic
Building Solutions from the MSBA approved list.
The
contract
with Strategic Building Solutions (SBS) was signed for a total amount of
$989,813 (page 28). The vote by the town for a feasibility study was in the
amount of $550,000. This contract was signed by former chairman of the board of
selectmen, Gerald Skelton on September 15, 2009. This contract was signed by
SBS on June 25, 2009. At the bottom of the first page, please note that the
contract was stamped “RECEIVED DEC 08 2010”. Received by whom? The BOS? None of
this makes sense, unless it was mixed in with the documents from 252
Baldwinville Rd in the white binder.
My
opinions…supported by FACTS ! ! !
Julie
Farrell