On Wednesday and Thursday Night, April 3rd and 4th, around 7 PM PJ Keating will commence:
• Milling Timpany Boulevard from around McDonalds up past the old Stop and Shop/Tops plaza
• Milling West Broadway from the State owned portion near the Department of Public Works up through the 2A/68 Intersection to around Warwick Road.
• Milling West Broadway from the State owned portion near the Department of Public Works up through the 2A/68 Intersection to around Warwick Road.
• Install temporary line markings
• Lights will go to timed setting due to loops being removed from milling
4 Police Officers will assist with traffic and pedestrians
Department of Public Works staff will be on hand to assist and provide signage
Department of Public Works staff will be on hand to assist and provide signage
Pavement will be grooved
structures will be elevated higher than the roadway surface –they will be painted
Area will be signed making public aware of grooved pavement and raised structures
structures will be elevated higher than the roadway surface –they will be painted
Area will be signed making public aware of grooved pavement and raised structures
PJ Keating will come back the following week to pave a leveler course
THIS IS NOT THE FINAL COURSE
THIS IS NOT THE FINAL COURSE
In the meantime:
**Unitil needs to run a gas service into the 99 site
This will require them to excavate in the leveler course
This will require them to excavate in the leveler course
**The 99 Contractor needs to run water and sewer from West Broadway into the site for future construction
This will require them to excavate in the leveler course
This will require them to excavate in the leveler course
Once all utilities are run into the 99 site, the City will come back and adjust all structures
Replace the deteriorated sidewalks in the area
Pave the road
Install Traffic Light Loops
Line paint
Replace the deteriorated sidewalks in the area
Pave the road
Install Traffic Light Loops
Line paint