Shedding
Some Light June 18, 2013
Last
night’s Light and Water meeting was well attended. The discussion with the
sewer commissioners has the first item discussed. The sewer commissioners are
looking for cooperation is shutting off water service for the most delinquent
or customers who blatantly refuse to pay their sewer bills.
The
other alternative for the sewer commission to pursue is installing a sewer
shutoff valve, which will entail BOH declaring the homes uninhabitable. The L+W
commissioners cited the legal opinion, which does not allow them to turn off
water service for sewer scofflaws. The Sewer commissioners requested that legal
opinion and the L+W commissioners voted to release that opinion to the Sewer
commissioners.
BUDGET –
The
L+W commissioners voted a new budget figure for FY 14 for $1,413,000. According
the GM Driscoll, this figure includes $30,000 in maintenance that will be
enough to cover the water improvements at the intersection of Baldwinville Rd
and Maple St. These improvements will be part of the Bald. Rd project and paid
for by the water department( $15,000 approximately).
It
is interesting to note that the citizen petition for the STM submitted by Ed
McClure is the exact same figure that was adopted last night by the commissioners.
GM
Driscoll asserted that the increase in the budget was minimal as a percentage.
There was no discussion about the sharp loss in revenue for the water
department or the necessity to double the service fee from $28/quarter
($112/year) to $56/quarter ($224/year) in order to achieve a balanced budget.
Water Rate Study-
The
water rate study by Tighe & Bond is expected to be completed by next month.
We won’t know if the customer
service charge will be part of the new water rates. The customer service charge
is not an optional fee, therefore in my opinion, I believe it should be included as part of the water rate.
STM Articles-
The
articles for the STM were discussed. It is the opinion of the GM that article 7
will not be a useful solution to the water budget appropriation. Article 6 was
discussed by the GM as well – the new bylaw for the water enterprise fund. The
GM stated the water enterprise fund does not operate under Chapter 44 section
53F1/2 of the Mass General Laws.
Questions -
The
question was raised that if the water enterprise does not operate under Chapter
44 53F1/2 then what section of Chapter 164 deals with enterprise funds? Let’s
hope there is an answer to that question by June 27th!
Mr.
Smart asked about contracts over $5,000. He left a copy of Chapter
164 section 56C, which states:
“Section 56C. Every municipal light commission or
manager thereof, who makes or executes a contract on behalf of a municipal
lighting plant, where the amount involved is five thousand dollars or more,
shall furnish said contract or a copy thereof to the city or town auditor
within one week after its execution. Said city or town auditor shall keep such
contract or copy on file, open to public inspection during business hours. Such
contracts or copies shall be kept in a separate book, arranged according to the
subject of the contract, or in other convenient form. An index of the subject
matter of the contracts and to the names of the contractors shall be made
semi-annually, and shall also be open to public inspection in some convenient
form. All allowances under and additions to such contracts, or copies thereof,
shall be filed with the city or town auditor, together with a sworn statement
of the officer making such allowances or additions that the same are correct
and in accordance with the contract. A city or town auditor, municipal light
commissioner or manager wilfully failing to comply with this section shall be
punished by a fine of not less than ten nor more than one hundred dollars.”
There
was no discussion on this topic.
Frank
Moschetti thanked the Light and Water commissioners for their support of the
Senior Center project and asked for support and cooperation when the foundation
borings are scheduled…again. Mr. Moschetti was assured that the L+W department
would cooperate.
Light Department Meeting
Bald. Rd project –
All
the poles except for 2 have been moved.
Rate Study-
In
discussion about the rate the GM Driscoll vented about the increase in arrears
from about $18,000 in 2003/2004 to about $66,000 currently. The lost revenue
stems from people leaving apartments with large bills unpaid. Electricity
cannot be turned off in the winter months, so some people leave their
apartments with large unpaid electric balances. An prior increase in deposits
for renters (from $200 to $500) was enacted in the hopes to curtail this
activity that ALL ratepayers must
cover.
OPEB Discussion-
OPEB-
other postemployment benefits were briefly discussed. MMWEC is reviewing OPEB figures for TMLWP. No decision has
been made to use MMWEC to administer OPEB or a private entity.
FOIA/Public Records
request –
GM
Driscoll notified the TMLWP Commissioners that his/their public record request
had been fulfilled by the BOS. GM Driscoll notified the TMLWP Commissioners
that he will exhaustively comb though the records provided on a pen drive to
locate a vote allowing one selectman to pull invoices. (See future blog – Would
YOU pay this invoice?)
GM
Driscoll then went on a lengthy diatribe of all the faults of the BOS,
specifically Julie Farrell. Apparently “it’s not over yet”. Couldn’t agree
more.
Then
GM Driscoll proceeded to rant about the advisory board and an unpaid bill from
FY 2012. While rambling on about unpaid local vendors because of the BOS
office, I felt some clarity was needed.
The
unpaid bill from FY 2012 will be addressed at the STM on June 27th
(Article 9). Because this item is an unpaid bill from a prior year, it needs Town meeting approval. ACTUAL town meeting approval; not the
advisory or non-binding kind of approval TMLWP are so fond of stating. It will
also require a 9/10’s vote. Because those are the rules for an unpaid bill from a prior year…not because the BOS are
trying to make your miserable life more miserable.
When
questioned about pulling local vendor invoices, GM Driscoll backed off …BECAUSE no local vendor invoices have EVER been pulled from either the Light
department nor the Water department vendor warrants. GM Driscoll is very
unhappy about the vendor warrant process.
What
GM Driscoll fails to realize is that the reduction in hours and the closing of
town offices on Fridays has had a major impact on the process and procedures
for ‘doing business’ in town. This reduction in force coupled with staff
turnover and new software systems has had an impact on the warrant process. The
alternative is to process your
payroll and vendor warrants by YOUR staff.
Customer questions –
Wind
turbine cost certification should be ready by the end of July.
Mr.
Smart asked about nuclear contracts and debt. 40% of TMLWP portfolio is
nuclear. The debt should be paid off by 2017. Decommissioning costs for nuclear
PSAs are variable. The department does receive RECs from Brodie MT wind farm
and the solar array at the TMLWP cost $58,000 (no debt) and does generate some
solar RECs.
Mr.
Driscoll did agree to attend the pre-town meeting tonight (Wednesday) at 690
Patriots Rd. at 6:00 p.m.
TMLWP
Commissioners voted to go into executive session.
My
opinions…supported by FACTS ! ! !
Julie
Farrell
It is too bad that these meetings are not recorded. The public would see their Commissioners at work. Mr. Driscoll carried on and on about the bill that was not paid. Chris Stewart knows the ropes. He could have corrected JD, but no!! It is easier to just sit and watch him go on and on!! It was not until Julie spoke up to inform JD of how things work, that Chris, finally opened his mouth. This is not going to be a easy job for Chris. In the end, he will have to work for his money. Isn't that why he is there?? He can do some good, and defuse some of this anger, by explaining how things work, or just sit and let things get worse. His choice!! My opinion, Bev.